track record

 

 

selected transactions


>
   CATEGORY: Track Record                                                                                                               SUB-CATEGORY: Advisory
   LOCATION:  Abu Dhabi / UAE                                                                                                        …. SPEC: 1,550MW

 


Project cost circa

$2.1bn

 Produces 114 million litres of desalinated water per day

 

  • Advised Abu Dhabi Water & Electricity Authority (ADWEA) on a 1,550MW natural gas CCGT
  • Project cost circa $2.1bn
  • Produces 114 million litres of desalinated water per day
  • The Umm Al Nar power and water project is 15km east of Abu Dhabi, in the UAE.
  • The plant has five 218MW gas-fired GE Frame 9351FA turbines. Five dedicated heat recovery steam generators (HRSGs) and two 308MW Toshiba back pressure steam turbines coupled to two Hitachi Zosen desalination units